Progress is really starting to show

Posted on Thursday, August 25, 2016

After just a few short months over winter, construction progress is really taking off at the terraces in Millwater Central. The architecture is starting to take shape as the final design of the building is revealed more and more each day.

Recent progress is on track and the next few months will see some key milestones reached:

  • All precast concrete flat slabs are now in place
  • Timber framing has commenced and progressing well for units 1-21, as well as units 26-33
  • All pre nailed framing will be on site by early September, with the aim to have it all in place towards the end of September
  • Roofing will commence in the next few weeks

Selected opportunities for retail space are still available:

9 of the 14 retail units have been leased or sold to owner occupier businesses, meaning there are only 5 retail units remaining. If you would like to see any particular businesses within Millwater Central or know of any businesses looking in the area, we are happy to discuss the opportunity with them.

Reminder: completion of the terraces is now anticipated for Febuary-March 2017.

With the construction industry under a lot of pressure and Council delays with consents, we are still expecting completion early next year.

Once again, the photos and video show just how much progress there has been, so please take a few moments to check out a selection of recent shots below, or view more in the gallery on our website.

Until next time,
Jan Hewitt: 027 595 2557

You can also watch this flyover video of the progress to date by clicking on the video below.

read more view comments ()

It's been a busy summer

Posted on Thursday, May 12, 2016

With shorter days and Autumn now upon us, we thought you’d like to hear details of the progress over summer at the terraces , Millwater Central.

We are making good progress, here are some construction updates:

  • block work is complete for the majority of the site, the garages and storage units are taking shape
  • the concrete floor in the basement is well under way
  • pre cast beams and structural steel for the retail and basement areas have been placed
  • installation of the podium slab floor has commenced at the south eastern end of the site
  • Up coming work will include:

  • finishing block work for the retail and basement areas
  • finish concrete floors for the retail and basement areas
  • continue with the podium slab floor and preparation for houses
  • Completion of the terraces is now anticipated for Febuary-March 2017.
    The main reasons are:

  • the construction industry is under a lot of pressure, affecting our suppliers' ability to meet targets
  • building consent delays with Council
  • I'm sure you are very keen to see photos of the progress, so please take a few moments to check out a selection of recent shots below, or view more in the gallery on our website.

    Please note, I wil be away until late June so will be unable to return calls or email enquiry until my return.

    Until next time,
    Jan Hewitt: 027 595 2557

    You can also watch this flyover video of the progress to date by clicking on the video below.

    read more view comments ()

    Construction is progressing well... and we're making the most of the good weather

    Posted on Friday, February 26, 2016

    After a wet and wild start to summer we hopefully have those delays behind us now, so all of us at the terraces are pleased to let you know the contractors are making good progress now the weather has improved. Excellent progress is being made to the foundations, underground services and concrete block walls that form the retail and basement carpark areas underneath your new home, the terraces at Millwater Central.

    As you may be aware, the construction industry is very busy at present, so we are working hard to continue the excellent progress already made on site.

    Progress we expect to see at the terraces in the coming months include:

  • Foundations and blockwork to continue along the Stables Lane area
  • Placement of structural steel to the retail area
  • Installation of precast beams and flat slabs which form the podium area followed by preparation of the concrete floor for your home
  • Works on the terraces framing above podium level are planned to commence early May
  • I'm sure you are very keen to see photos of the progress, so please take a few moments to check out a selection of recent shots below, or view more in the gallery on our website.


    You can also see some fantastic flyover videos, including a panorama of the views from your living and bedroom levels, by clicking on the video below.


    Here's to a nice long summer with plenty more progress as we move on to the next stage. As always please don't hesitate to contact me should you have any questions about your new home. 

    Until next time
    Jan Hewitt: 027 595 2557

    read more view comments ()

    Terraces architect wins at NZIA awards

    Posted on Monday, June 01, 2015

    Julian Guthrie of Godward Guthrie Architecture Ltd and designer of the terraces at Millwater Central, are delighted to announce a double success at the New Zealand Institute of Architects Auckland Architecture Awards for 2015.

    Their Muriwai House won in the new Housing category and their Meadowbank House won in the Housing - Alterations and Additions category. 

    Click the images to view the houses more detail.

    read more view comments ()

    Terraces show home now open

    Posted on Saturday, April 11, 2015

    Millwater, Auckland’s most popular new suburb, has an exciting new addition coming to the heart of this thriving community.

    The terraces at Millwater Central utilise a timeless contemporary design by the multi award-winning architect Julian Guthrie. Consisting of 37 high quality three bedroom homes, the terraces have been thoughtfully designed to maximise coastal views and sunshine. Every terraced home enjoys a fully secure landscaped environment, including an expansive central courtyard and spacious interiors that flow on to generous private outdoor living areas. Double undercover car parking and storage are also included.

    The terraces genuinely offer the ultimate urban lifestyle, just moments from a selection of cafés, shops and services. The area has a wide variety of schools, parks and recreational activities, and benefits from easy access to public transport and motorways. 

    These homes provide quite a unique addition within this diverse community and promise to sell quickly. But don’t just take our word for it, come and visit our show home at Millwater Central between 11am and 3pm daily. Alternatively, feel free to call Jan or Serena to make an appointment. We look forward to hearing from you soon. 

    Jan Hewitt: 027 595 2557
    Serena Stevens: 021 368 611

    read more view comments ()